By Dennis Lynch, BS MechEng MIT, MS CivEng MIT and Fergus Nolan, BS, MA.
New: Our LNP Plan FAQ
in which Manny Belen's, the City Engineer's response to the LNP is dissected and the nature of the planning problem revealed.
Belen's letter is a mixture of misinformation and inadequate care taken to read the proposal. He's writing more like a politician or a marketer than an engineer.
I actually expected better of Manny Belen. You did not go to engineering school to lern how to manufacture fake news.
This document was submitted to Powers Hill on 6/23/2016 and they shared it with the City Engineering Dept. It will be considered in the upcoming public input sessions. The .pdf version submitted to the design consultants is here.
The Zoo currently has 213 spaces in Prentiss lot and 654 in the Main Lot for a total of 867 spaces. The
Parking Plan calls for an additional 415 spots to provide a total of 1282 spots.
Although the City Council resolution does not require amelioration of additional issues with Zoo access,
we feel that the opportunity provided by this parking redesign is too good to miss. In fact, due diligence
to our supporters, subscribers, taxpayers and the City Council requires all concerned to obtain the best
possible value from the development.
The major issue we question is the non-optimal traffic pattern around the Zoo. On busy days, traffic starts building up more than thirty minutes before the 09:00 Zoo opening time. It backs up on Morrie Moss Lane and the south leg of Prentiss, all the way out on Poplar where the westbound inside lane sometimes backs up for hundreds of yards. It also backs up on North McLean and on both the eastbound and westbound lanes of N Parkway. The major influx can last for several hours beyond 08:30, and there is often a smaller traffic backup between 12:00 and 2:00. There is also a Tuesday afternoon backup on popular free attendance days.
Although inbound Zoo traffic comes with two peaks, Zoo visitors start leaving by noon and leave throughout the day, with a minor peak at closing time. Outbound traffic rarely backs up outside the Zoo.
Good traffic planning and engineering would have Zoo-bound traffic enter from the regional street network and not through the Park. Why should Park visitors have their quietude and their peaceful enjoyment of the Park disrupted by traffic passing through on their way to the Zoo? Additionally, Zoo traffic passing through the Park is unsafe for Park users, pedestrians and bicyclists.
a) Is a "maximum density parking plan", with the objective to show that the City Council
resolution's requirement can be massively exceeded without taking any space from the
Greensward or Little Greensward. With the parking requirement massively exceeded, we expect
that the Consultants and City Engineering can improve this rough plan in many ways.
b) Provides 2304 spaces, over 1000 more than the City Council has specified. (A refined plan might
reduce the number of spaces by 100-200.)
c) Completely protects the Greensward and Little Greensward
d) Saves the Park from Zoo traffic traversing the Park to get to the Zoo, with safety, noise pollution
and air pollution benefits
e) Frees up Overton Park's parking spaces for use by Park users
f) Provides protected pedestrian pathways through the parking to the Zoo entrance
g) Provides ADA parking at the closest location to the Zoo entrance, as required by law
h) Substantially reduces parking in the Evergreen neighborhood
Two major causes were observed. Firstly, the single-threaded parking shack for the main lot, and the
additional temporary payment point at Prentiss create bottlenecks. Secondly, North McLean is a narrow,
two-lane street, and there is no separate left turn lane at Prentiss for southbound traffic wishing to enter
the Zoo.
We suggest two traffic improvements.
1. Parking payment should be collected after the vehicle is parked. The design consultants should
evaluate and propose a suitable parking fee collection process.
2. Stop driving through the Park or on North McLean to enter the Park. Use North Parkway, where
the a service entrance to the Zoo already exists. A pathway to the eastern end of the
parking lot by internal Zoo roadbeds already exists to a large extent. All departing traffic exits at
the west end of the current Prentiss lot, with a right-turn-only exit northwards on N McLean.
In addition, all vehicular access from the south is prevented by a permanent fence, with a keyed access
for emergency vehicles, across the Prentiss roadbed, and regular access for pedestrians and cyclists only.
Closing the Morrie Moss entrance will eliminate the emissions and traffic hazards to other Park users,
and improve the Park experience for all.
The linked Figure 1 shows our proposed parking plan, which yields an estimated 2304 parking places.
|
Original Proposal |
Our Plan |
Parking on existing footprint |
867 |
|
North Parkway on-street |
200 |
200 |
Produced by parking plan |
415 |
2304 |
Total parking |
1482 |
2504 |
Extra parking yield |
|
1022 |
This is 1022 more spots than the Zoo needs. Download the full-sized 40 MB graphic here.
How we created Figure 1: See Appendix 1.
The 1022 additional spaces in the plan, which are surplus to requirements, provide a lot of options for meeting the Zoo’s parking needs while actually giving back a part of the southern portion to the Park. The plan closes Prentiss as a public street, and also incorporates the new parking area east of the Main Lot, which the Zoo has been using, and running shuttles to, this year.
The drone starts at the N. Parkway entrance and flies north for 30 seconds, then turns right to show the eastward path to the main lot. Drone courtesy of Coalition of Concerned Citizens.
Figure 2 is a sketch of the access available to the parking lot from the North Parkway entrance, which is
currently a works entrance to the Zoo and also a barricaded entrance to the Old Forest roadbeds.
The N Parkway access point has left and right turn lanes into the entrance. The westbound left turn lane
could be extended eastwards and provided with an on-demand left turn light, as determined by City
Traffic Engineering.
Point A is the N Parkway entrance to the Park. A 3-lane wide asphalted roadbed extended less than 200
feet south to a barrier at point B.
At point B, to the west, the Zoo main service entrance. A concrete roadbed, about 10 to 12 feet wide, follows the inside of the Zoo fence to point C. This roadbed could be extended with a crushed rock shoulder and reused for Zoo entry. The Zoo fence would need to be moved to the west side of this driveway. A low vehicle barrier can be used between this road and the parallel Park road, which is closed to vehicular traffic. This driveway is about 800 feet long. The 90 degree bend near point C probably needs to be modified to a more gradual curve to allow 20 MPH turns without braking.
It is important to
note that 3 uses are
needed between B &
C, and there is
sufficient width to
accommodate all 3.
The uses are- zoo
service road, zoo
parking access road,
and pedestrian path
around the Old Forest.
At point C, there is a
gate in the fence, a
small building and the
end of the southward
part of this concrete driveway. The driveway turns westwards at this point and follows the Seventeen
Acre fenceline for about 240 feet to a point south of Elk Rut, point D. Much of this piece is already
fenced, and there appears to be room for a limestone shoulder.
From point D to point E, a distance of a little over 100 feet, is the western boundary of the Elk Rut and a
small space between the elevated pedestrian structure between Elk Rut and the Grizzly Bear exhibits in
Teton Trek. This space is tight and might require concessions but there appears to be a little over
20 feet here for the access drive.
From points E to F, there is a grassy area, which will accommodate a new roadbed, to the south of an
asphalt walkway which forms the southern boundary of the Zoo customer area.. This is about 100 feet long.
Points F to G mark a wide asphalt roadbed which is used for Zoo pedestrian access to Teton Trek. It is very wide, more than 20 feet. It is skirted to the south by a wide grassy area and the Seventeen Acre fence is further south. Some of the existing roadbed could be used, extended to the south. There is enough space here for additional Zoo parking of up to 100 vehicles not shown in Figure 1.
At point G, we have a large area currently used for Zoo employee and visitor parking, some of which is shown in our
plan. The chain-link gate which connects this area to the main lot is here.
In summary, the entrance route mostly requires new fencing, the addition of a crushed rock shoulder, to
accommodate disabled vehicles and emergency access, about 200 feet of new roadway engineering and
modest widening of the remaining existing asphalt driveways. This route is viable. The first parking is
available about 400 feet west of point F.
As there will be no need to stop to pay for parking at entrance, and as there is no cross traffic or turns
across other traffic, this route will be able to support a steady stream of uninterrupted one-lane traffic
and customers should be able to get access to the parking in a minute and a half at 20 mph, for a total
driveway length of about 2000 feet.
This path to the parking will be substantially quicker than existing routes through the Park or along N.
McLean. It will eliminate the queues and pollution of the current paths through the Park and on Morrie
Moss, McLean, Poplar, and N.Parkway.
This plan exceeds expectations handsomely along several vectors and can form the basis of a plan that
will please all concerned, Park Protectors, the Zoo, and the neighboring residents who will enjoy better
traffic flow. It also protects the remainder of the Park completely from Zoo traffic and the attendant
emissions. The Zoo visitors’ experience and convenience will be greatly enhanced.
How we created Figure 1.
We printed the map from Google earth
The scale was measured, 50 feet being 0.622 inches as measured by calipers.
Access driveways, marked in black, run east to west and around the perimeter. They are 22 feet
wide, enough for two lanes, although the majority of traffic will flow westwards unless someone
doubles back. The scaled size was 0.274” rounded to 0.27”.
The width of each spot is 9’, scaled as 0.112” rounded to 0.11”
The depth of each spot is 19’, scaled to 0.236”, rounded up to 0.24”
32 ADA compliant disabled spots had 5’ or 8’ unloading spaces added and there are four van
accessible spaces. These are arrayed around Zoo Plaza as the nearest possible spaces to the Zoo
entrance.
We added 9’ wide protected pedestrian / cycle access paths at 250’ intervals.
We counted 60 mature trees in the lot and reserved 90 spaces so that mature trees can be
retained, based on an algorithm that assumes trees are distributed randomly. We were unable
to plot the individual tree positions. There are lots of small trees under 6” in diameter which
can be either moved or replaced with similar sized trees.
As our roundings were both up and down, we feel, based on our QA, that the parking map is
accurate to within plus or minus 5%.